By the NGOs.ke Editorial Team
A grant budget for a Kenyan NGO has to do two jobs at once: show the donor exactly what each shilling buys, and cover the real cost of running the project in Kenya, including the payroll costs that never appear on a staff member’s offer letter. The short version: build the budget line by line from your activity plan, cost salaries at gross pay plus the employer’s statutory contributions (NSSF, the Affordable Housing Levy and the NITA levy), state your exchange-rate assumption, and separate direct costs from indirect costs the way the donor’s template asks. Get those right and most of the back-and-forth with a programme officer disappears.
Most of the grant-budget guides that rank today are written for American or Canadian nonprofits. They’re useful on structure, but none of them tells you that from February 2026 an employer in Kenya pays up to KES 6,480 a month in NSSF for a single employee. That gap is where Kenyan proposals quietly lose money, so this guide covers it in figures that are current as of November 2026.
What should a grant budget include?
Donor templates differ, but almost all of them ask for the same building blocks. If your budget has these, you can map it onto nearly any format:
- Personnel: each post, its gross monthly salary, the percentage of time charged to this project, the number of months, and the employer’s statutory on-costs.
- Activities: trainings, community meetings, campaigns and the like, costed by unit (per participant, per day, per session) and not as one lump sum.
- Travel and transport: fuel, vehicle hire, public transport refunds, per diems and accommodation, with the rates your own finance policy sets.
- Equipment and supplies: anything with a lasting value, which donors often treat differently from consumables.
- Monitoring, evaluation and audit: baseline and endline surveys, data collection tools and the external audit the grant agreement will almost certainly require.
- Indirect costs: a share of rent, utilities, finance and management time, charged at whatever rate the donor allows.
- A budget narrative: one or two sentences per line explaining how you arrived at the figure.
If you’re still at the concept stage, our guide to writing a concept note donors will read covers how the summary budget should look before you build the detailed one.
How do you budget staff costs in Kenya in 2026?
This is the line Kenyan NGOs get wrong most often. A budget that lists only gross salaries will run short, because the employer pays several contributions on top of gross pay. Here are the 2026 rules that matter for a donor budget:
| Contribution | Who pays | 2026 rate | Budget impact |
|---|---|---|---|
| NSSF (Year 4, from 1 Feb 2026) | Employer and employee, 6% each | 6% of pensionable pay between the lower limit of KES 9,000 and the upper limit of KES 108,000 | Employer share up to KES 6,480 a month per employee |
| Affordable Housing Levy | Employer and employee, 1.5% each | 1.5% of gross pay, no cap | Employer share is an extra cost on top of salary |
| NITA Industrial Training Levy | Employer only | KES 50 per employee per month | Small, but it adds up across a large team |
| SHIF (Social Health Insurance Fund) | Employee only, deducted by employer | 2.75% of gross, minimum KES 300, no cap | Already inside gross pay, so no extra employer cost |
| PAYE | Employee, deducted by employer | Bands from 10% to 35%, personal relief KES 2,400 a month | Already inside gross pay |
The PwC Kenya tax alert on the Year 4 NSSF rates puts the combined maximum at KES 12,960 a month, split equally between employer and employee. It also notes that Year 4 completes the phased schedule under the NSSF Act, so any future change will come through a gazette notice and not on an automatic yearly step. That’s worth a footnote in any budget running into 2027 and beyond.
A worked example: a programme officer on KES 100,000
Say a programme officer earns a gross salary of KES 100,000 a month and works full time on the project. The employer’s monthly cost is:
- NSSF employer share: KES 540 (Tier I) + 6% of KES 91,000 (Tier II) = KES 6,000
- Affordable Housing Levy, employer share: 1.5% of KES 100,000 = KES 1,500
- NITA levy: KES 50
That’s KES 7,550 a month, or about 7.6% on top of gross pay. Over a 12-month grant it comes to KES 90,600 for one post, which is roughly a month’s salary. For an officer on KES 60,000 the on-cost is KES 4,550 a month, still about 7.6%. Once a salary goes above the KES 108,000 NSSF ceiling the percentage drops: on KES 250,000 it’s KES 10,280, about 4.1%.
The simplest approach is to add an “employer statutory contributions” line under personnel, calculated per post, and to explain the formula in the narrative. Programme officers at most donors recognise it straight away when it’s shown openly. If you hide it inside a rounded-up salary, it tends to draw questions.
Direct or indirect: where does each cost go?
A direct cost exists only because of this project: the field officer hired for it, the training venue, the baseline survey. An indirect cost keeps the whole organisation running and is shared across projects, such as the finance manager’s time, office rent, internet and the annual audit of the organisation’s books.
Donors handle indirect costs in very different ways. Some allow a flat percentage, some want a negotiated rate backed by audited figures, and some allow nothing at all and expect shared costs to be broken out as direct lines. Our breakdown of indirect cost rates for Kenyan NGOs sets out what the main donor types accept and how to work out your own true rate.
How do you handle currency and inflation?
Many donors approve budgets in US dollars, euros or pounds, but you’ll spend in shillings. Say in the narrative which exchange rate you used and on what date, and ask the donor how they treat exchange gains and losses. Some let you reprogramme a gain, and others want it reported and returned. For grants of more than a year, a modest yearly increase on salaries and on prices such as fuel and venue hire is normal practice, as long as you state the percentage and the reason.
Common mistakes that get NGO budgets sent back
- Lump sums. A line reading “Community training: KES 450,000” with no unit cost almost always gets queried. Show participants × days × cost per person.
- Numbers that don’t match the activities. If the proposal promises six county workshops, the budget should cost six, not four.
- Missing compliance costs. External audit, data protection measures and the payroll contributions above are real costs. Put them in.
- Procurement assumptions that break your own policy. If your policy requires three quotations above a set threshold, cost the item at a realistic market price. Our guide to NGO procurement policy thresholds explains how to set them.
- A narrative that repeats the table. The narrative should say why, for example “per diem at the organisation’s approved rate of KES X for county travel”, not restate the figure.
For official guidance on the training levy, including the paybill and registration rules, the National Industrial Training Authority’s levy page is the primary source. When the budget is finished, our step-by-step guide to writing a grant proposal for a Kenyan NGO covers the narrative sections that sit around it.
Frequently asked questions
Should I include NSSF and the Housing Levy in a donor budget?
Yes. The employer’s share of NSSF (up to KES 6,480 a month per employee from February 2026) and the 1.5% employer Housing Levy are legal costs of employing staff in Kenya. Show them as a separate personnel line with the formula in the budget narrative.
Is SHIF an employer cost in Kenya?
No. SHIF is 2.75% of gross pay (minimum KES 300) deducted from the employee and sent on by the employer. Because it comes out of gross salary, it isn’t an extra cost in your budget.
How much should staff on-costs add to a Kenyan grant budget?
On salaries up to about KES 108,000 a month, the employer’s NSSF, Housing Levy and NITA contributions together add roughly 7.5% to 7.6% of gross pay. Above that NSSF ceiling the percentage falls, because the NSSF amount stops rising.
What is the difference between a grant budget and a budget narrative?
The budget is the table of costs. The narrative, also called the budget justification, explains each line: how it was calculated, why it’s needed and how it links to a project activity.
Can I charge my office rent to a grant?
Usually, either as an indirect cost through the donor’s allowed overhead rate or as a shared direct cost split by a clear basis such as staff time or floor space. Check the donor’s rules first, because some don’t accept both methods together.